Bowtie Analysis: Bow Tie Risk Assessment & Diagram Guide
Bowtie analysis (also written 'bow tie analysis') is a visual risk assessment method that places one Top Event in the centre of a bow tie diagram, with threats on the left, consequences on the right, and the preventive and mitigating barriers controlling each pathway.
The bow tie risk assessment model emerged from oil & gas safety practice in the 1990s and is now mandated or recommended by regulators worldwide. A well-built bowtie diagram makes a complex risk picture legible to non-specialists in a single page — exactly what boards, regulators and frontline crews need. RiskoPilot's investigation engine generates a fully populated bowtie analysis from your incident narrative in minutes, then keeps it linked to your Tripod Beta tree for end-to-end traceability.
BY RiskoPilot Editorial Team · REVIEWED 2026-06-20
How it works
- STEP 01
Define the hazard
Identify the hazardous activity or substance whose loss of control you want to model in the bow tie diagram.
- STEP 02
Place the Top Event
Specify the moment of loss of control in operational terms (e.g. 'unintended hydrocarbon release') — this anchors the centre of the bow tie.
- STEP 03
List threats
Brainstorm every credible cause that could trigger the Top Event. Each threat becomes its own line on the left side of the bowtie diagram.
- STEP 04
List consequences
Identify each credible outcome if the Top Event occurs (people, environment, asset, reputation) — these populate the right side of the bow tie.
- STEP 05
Map barriers
On each threat line add preventive barriers; on each consequence line add mitigating and recovery barriers. Note degradation factors that weaken each barrier — this is the core of bow tie risk assessment.
- STEP 06
Assign owners and verify
Assign each barrier to a responsible role and review barrier health periodically as part of your management-of-change cycle.